NTPC Kayamkulam

Rajiv Gandhi Combined Cycle Project.

One of the major power production centers in Kerala.

Address     P.O. Choolatheruvu,Dist. Alappuzha-690 506,Kerala
Fax     2472706

Approved capacity     350 MW
Installed Capacity     350 MW Net (Gross – 359.577 MW)
Location                                 Choolatheruv,Allappuzha, Kerala
Fuel Source                           Imported/Indigenous Naphtha
Water Source                       Sweet Water from Achankovil river
Beneficiary States              Kerala & Tamil Nadu (with consent of Kerala)
Approved Investment       Rs.1189.94 Crore
Unit Sizes Gross                   2×115.2 + 1×129.177
Units Commissioned          GT 1 – November 1998
GT 2 – February 1999
ST – October 1999
International Assistance  Time slice loan of World Bank.